Thank You, North Plainfield -- Bond Referendum Approved!
The Somerset County Clerk’s Office has certified the results of the September 16 vote, with 741 votes in favor and 178 opposed.
What's Next?
- Spring 2026: Project Bidding Begins
- Summer 2026: Sell Bonds: Referendum Financing
- Summer 2026: Start Projects
Several factors will determine the order projects are completed. Some projects will be scheduled in the summer months to avoid disrupting classes. Others will depend on the availability of contractors or equipment. All projects are forecasted for completion by fall 2029.
Projects
- HS & MS Science Labs
- HS Media Center
- HS Auditorium
- HS Culinary Arts Program
- HS Locker Rooms
- HS & Elementary Security Vestibules/ADA Ramps
- HVAC Upgrades
- Window Replacements
HS & MS Science Labs
HS Media Center
HS Auditorium
HS Culinary Arts Program
HS Locker Rooms
HS & Elementary Security Vestibules/ADA Ramps
HVAC Upgrades
Window Replacements